Schedule Performance Index (SPI)

Project Management

SPI measures schedule efficiency by comparing earned value to planned value.

Definition

SPI measures schedule efficiency by comparing earned value to planned value.

Formula

SPI = EV / PV

Explanation of Variables

EV = Earned Value
PV = Planned Value
Advertisement Space

Calculator


Result: —

Worked Example

EV = 80,000
PV = 100,000

SPI = 0.8

Industry Use Case

Used to track whether a project is ahead or behind schedule.

Related Formulas

Cost Performance Index(CPI)

Project Management

CPI measures cost efficiency by comparing earned value with actual cost.